Intermain carried out their program within a live environment, during two school terms. Working in an operational school, meant careful consideration and seamless execution was required due to the level of complexities working with stakeholders that involved children with special needs.
Client
Woody Point Special School, QLD
Location
Redcliffe Peninsula, QLD
Project Manager
Lambert & Rehbien
Delivery Model
Construction Management
Floor Area
1,000 sqm
Construction Duration
18 weeks
To address the unique challenges, Intermain worked out of hours to keep noise levels at a minimum as some children were sensitive to particular sounds. The needs also varied from child to child; hence frequent and transparent communication was imperative to the success fo of the project.