The owners purchased the dilapidated warehouse and looked to Intermain to complete a makegood and refurbishment of the asset with a roof replacement, new facade and a racking system. Major works of the project involved the demolition and removal of existing cold rooms, amenities, and an office, in addition to the demolition and disposal of asbestos roof sheets.
Client
Livingstone International
Location
Broadmeadows, VIC
Project Manager
Knight Frank
Delivery Model
D&C
Floor Area
7,000 sqm
Construction Duration
20 weeks
A significant challenge was the extensive council approvals required to remove the existing roof system, which was entirely asbestos. Our team overcame this through comprehensive pre-construction documentation, and a highly organised approach to coordination between the parties.