The 10,000 sqm project, a lump-sum Design and Construction contract, required a complete industrial refurbishment and fitout of Building 1 at 34-42 Sheppard Street Hume ACT.

Client
Goodman
Location
34-42 Sheppard St, Canberra
Delivery Model
Lump-sum
Floor Area
10,000 sqm
Construction Duration
16 weeks
The scope of works included a three-tier mezzanine racking system, essential services and power upgrade. In addition, the existing offices were refurbished and executed with an integrated fitout.


Key challenges included extensive cold and wet weather, extremely hard ground conditions and a very tight program.